Page 70 - Sinergia 56 | 2020
P. 70
AFRICA
3
EXECUTION METHODOLOGY FOR THE 1ST PHASE:
1. HZM combined wall driving (currently PK 235) – 100%;
2. Digging of the inside of the breakwater (currently PK235) – 100%
3. Placement of tie rods (currently PK235) – 100%
4. Embankment with sand from the beach to level +3.50 (currently PK235) – 100%
5. Vibro-compaction of the embankment at level +3.50 – (currently PK235) – 100%
EXECUTION METHODOLOGY FOR THE 2ND PHASE:
Given that it is presently impossible to have a dredger
for the supply of sand and
the creation of the following embankment platforms, in order to proceed with the execution
of the sheet piling in the 360 m of pier (width of 40 m).
Estimated dredging volume required for the 2nd phase (phase 2 and 3 in the following drawings) = 150,000 m3.
At the end of July, the driving of piles planned for the first phase was completed.
3
Aerial view
of the breakwater.
depth pier with berthing capacity for vessels up to 15,000 metric tons (cargo terminal);
The access path section will be 295 m long and 12.25 m wide. The length of the section on the sea side will be 365 m and its width will be 39.80 m.
The inner containment curtain of the breakwater will be used as a docking structure along two piers with different depths. The soffit of the initial section
of the breakwater will be used as a pier with an operating level of -5.00 m (LAT) and a length of 180 m. The main pier will be located on the soffit section of the side facing the sea. This pier will have an operating bottom level of -9.00 m (LAT) and a length of 340 m.
In the soffit of the breakwater,
in the area of inflection, in the transition between the two sections of the breakwater, a roll-on/roll-off (Ro-Ro) ramp will be built.
The ramp will be 25 m wide and 30 m long, and it will have a 10% slope.
70