THE CHALLENGE
In view of the execution period of only 14 months and the challenge of delivering 582 completed rooms in almost one year, the supply of 444 prefabricated bathrooms was chosen.
This solution enabled reducing labour, waste and, most importantly, the execution period, since the bathrooms come completely finished (with sanitary ware, mirrors, taps, ceramics) only
requiring putting them in their locations pre‐defined in the project.
This solution enabled completing 444 bathrooms in just three months.
In order to complete the remaining works within the proposed deadlines, it was decided to divide the work into several different work fronts with different teams, which resulted in an average load of 200 workers per day on site.
EARTHMOVING:
35,750 m3
REINFORCED STEEL:
1,571 metric tons
CONCRETE:
11,700 m3
FORMWORK:
45,100 m2
PILES Ø600 mm:
3,750 ml
GUNITING:
1,650 m2
ANCHORAGE 400/450Kn:
86 un
CERAMIC SURFACE:
12,750 m2
PLASTERBOARD ON WALLS:
24,950 m2
PLASTERBOARD ON CEILINGS:
13,400 m2
DISTENDED METAL FAÇADES:
5,675 m2
CAPPOTTO:
3,720 m2
Project
RELEVANT QUANTITIES
2
1
Status of the Work
on 28/05/2019 (8 months)
2
Prefabricated bathroom